Object

VALP Main Modifications

Representation ID: 3535

Received: 15/12/2019

Respondent: Hampden Fields Action Group

Legally compliant? Yes

Sound? No

Representation:

1. The modified text states that Woodland homes are projected to be delivered some time from 2021. AVDC's Strategic Development
Management Committee were advised that no residential land
would be brought forward in the first 5 years (Officer report
16/01040/AOP, para 9.33, October 2017)
2. Uncertainty expressed by a previous inspector and supported by
the Ouseley Manor Oak judgement is relevant across the whole
Transport Strategy (see comment below on MM202 and MM203)
but we draw the Inspector's attention to it in this section as well.
The uncertain delivery of Woodlands (see MM048 below) means
that delivery of the ELR(S) and the SEALR are uncertain despite
BCC's assertions.

Change suggested by respondent:

Full remedial action to correct the errors and gaps in the transport evidence base and modelling,
followed by a revised set of proposals including funding plans and timetable, with public consultation
on these modifications.

Full text: