Results for Thames Water search

New search New search

Object

VALP Main Modifications

MM017

Representation ID: 3563

Received: 16/12/2019

Respondent: Thames Water

Legally compliant? Not specified

Sound? Not specified

Representation Summary:

No explanation is given as to why the sentence:

"Infrastructure should be delivered in a timely manner and integrated alongside new development, with the specific phasing to be determined in agreement with the local planning authority"

Thames Water request further explanation as to why this is being removed, or where this may have been re included?

Full text:

See attachment

Object

VALP Main Modifications

MM045

Representation ID: 3564

Received: 16/12/2019

Respondent: Thames Water

Legally compliant? Not specified

Sound? Not specified

Representation Summary:

Paragraph 4.61 is proposed to be deleted. Thames Would like to know where information on phasing will not be supplied as this information is critical to them ensuring the required infrastructure is in place prior to occupation.

Full text:

See attachment

Object

VALP Main Modifications

MM076

Representation ID: 3565

Received: 16/12/2019

Respondent: Thames Water

Legally compliant? Not specified

Sound? Not specified

Representation Summary:

Revised policy states:
"w. An updated assessment of sewerage capacity and water supply network shall be carried out, working with Anglian Water, to identify the need for infrastructure upgrades and how and when these will be carried out to inform site delivery."
For consistency the same wording should be included in all allocation referencing Anglian Water, or Thames Water.

In addition part v. should read:
"v. A foul water strategy is required to be submitted to and approved in writing by the Council in conjunction with the water and Sewerage undertaker. "
This should also be included for every allocation.

Change suggested by respondent:

Revised policy states:
"w. An updated assessment of sewerage capacity and water supply network shall be carried out, working with Anglian Water, to identify the need for infrastructure upgrades and how and when these will be carried out to inform site delivery."
For consistency the same wording should be included in all allocation referencing Anglian Water, or Thames Water.

In addition part v. should read:
"v. A foul water strategy is required to be submitted to and approved in writing by the Council in conjunction with the water and Sewerage undertaker. "
This should also be included for every allocation.

Full text:

See attachment

Object

VALP Main Modifications

MM276

Representation ID: 3567

Received: 16/12/2019

Respondent: Thames Water

Legally compliant? Not specified

Sound? Not specified

Representation Summary:

The wording for Policy I5 has been amended to say:

"On major developments where development could have an impact on water resources and wastewater infrastructure capacity, early consultation is advised with either......."

We request that this remains as required not advised.

Change suggested by respondent:

The wording for Policy I5 has been amended to say:

"On major developments where development could have an impact on water resources and wastewater infrastructure capacity, early consultation is advised with either......."

We request that this remains as required not advised.

Full text:

See attachment