Aylesbury Vale Area

VALP Further Main Modifications

Search Representations

Results for Carter Jonas - Associate SWMK Consortium search

New search New search

Object

VALP Further Main Modifications

FMM057

Representation ID: 3998

Received: 23/02/2021

Respondent: Carter Jonas - Associate SWMK Consortium

Agent: Carter Jonas - Associate SWMK Consortium

Legally compliant? Yes

Sound? Yes

Representation Summary:

The number of dwellings to be delivered between is incorrect and is not consistent with the allocation or the current planning application at the site.

Change suggested by respondent:

The number of dwellings to be delivered between 2025 and 2033 at Site Allocation NLV001 should be corrected to be consistent with the allocation and current planning application at the site. It is requested that the figure 1,705 is replaced by 1,555 dwellings. As such, the predicted housing delivery at Site Allocation NLV001 should be 300 dwellings between 2020 and 2025 and 1,555 dwellings between 2025 and 2033.

Full text:

See attached documentation

Object

VALP Further Main Modifications

FMM058

Representation ID: 4001

Received: 23/02/2021

Respondent: Carter Jonas - Associate SWMK Consortium

Agent: Carter Jonas - Associate SWMK Consortium

Legally compliant? Yes

Sound? No

Representation Summary:

Planning Officer Summary
An additional allocation should be made to the south west of Milton Keynes at Site Ref. NLV020. A development at Site Ref. NLV020 could be accommodated without significant landscape and visual effects and would provide an appropriate transport mitigation package to enhance strategic and local transport infrastructure. It is considered that Site Ref. NLV020 is a better site than WHA001 in landscape and transport terms, and should be allocated accordingly.

Change suggested by respondent:

No changes are requested for FMM058. The SWMK Consortium maintains an objection to MM074 and changes to WHA001: Shenley Park are requested in those representations.

Soundness failed - not justified or consistent with national policy

Full text:

See attached documentation

Object

VALP Further Main Modifications

FMM105

Representation ID: 4002

Received: 23/02/2021

Respondent: Carter Jonas - Associate SWMK Consortium

Agent: Carter Jonas - Associate SWMK Consortium

Legally compliant? Yes

Sound? No

Representation Summary:

Planning Officer Summary

Only 500 dwellings will be delivered from site HAL003 during the plan period i.e. 500 dwellings fewer than currently predicted

Not sound - Not positively prepared, justified or consistent with national policy

Change suggested by respondent:

It is requested that the housing delivery timetable for HAL003 is amended to show that delivery would commence in 2028/29, on the basis that site closure would occur in 2025/26, no development would be delivered prior to full closure, and it would take two years to complete pre-development planning tasks.

Full text:

See attached documentation

Support

VALP Further Main Modifications

FMM105

Representation ID: 4003

Received: 23/02/2021

Respondent: Carter Jonas - Associate SWMK Consortium

Agent: Carter Jonas - Associate SWMK Consortium

Representation Summary:

The SWMK Consortium supports the predicted housing delivery timetable for Site Allocation Ref. NLV001 included in the revised housing trajectory.

Full text:

See attached documentation

Object

VALP Further Main Modifications

FMM089

Representation ID: 4005

Received: 23/02/2021

Respondent: Carter Jonas - Associate SWMK Consortium

Agent: Carter Jonas - Associate SWMK Consortium

Legally compliant? Yes

Sound? No

Representation Summary:

Planning Officer Summary

The new link road for Shenley Park should be a requirement and should be a grid road.

Not sound - not justified or consistent with national policy

Change suggested by respondent:

It is requested that the following additional modification is made to FMM089 at Table 16 to Policy T3:
Edge of Milton Keynes (North East Aylesbury Vale) - New roundabout access on A421 to serve Shenley Park and subject to more detailed traffic modelling possible dualling between new access and Bottledump roundabout and link road grid road through the site connecting the A421 with H6 and/or H7.
(see attached document for change's formatting)

Full text:

See attached documentation